Texas's grid
Grid operator and reliability
ERCOT. Most of Texas is ERCOT; the Panhandle and eastern edges sit in SPP and MISO, and El Paso is on the Western grid.
NERC area Texas RE-ERCOT: anticipated reserve margin 28.2% for summer 2026, against its reference level of 13.75% (+14.4 points). NERC rates the area elevated risk; later years: High from 2029.
Source: NERC 2025 Long-Term Reliability Assessment (January 2026).
Recent public decisions
Each checked against its document on October 30, 2026.
- September 18, 2026, Public Utility Commission of Texas: Large load interconnection standards adopted under Senate Bill 6. The Commission adopts new 16 TAC 25.194 under Project No. 58481, implementing PURA 37.0561 as enacted by Senate Bill 6, effective October 8, 2026. The rule applies to a large load customer not energized by that date that seeks a new interconnection of 75 MW or more at a single site, certain expansions, or co-location with a generation resource. Before being included in an ERCOT interconnection study, the customer must sign an intermediate agreement, make required disclosures, and post financial security of $50,000 per MW of requested peak demand. Under the later standard interconnection agreement, the security is the greater of $50,000 per MW of contracted peak demand or the costs allocated for system upgrades. The preamble leaves parts of the standard large load interconnection agreement, including the timeline for returning security, to a separate rulemaking, and says transmission cost recovery will be addressed in Project No. 58000. Texas Register, October 2, 2026, Adopted Rules, 16 TAC 25.194 (TRD-202604027)
- September 14, 2026, ERCOT: Data center energizations paused pending state verification and audit. ERCOT's Batch Zero update to its Board says Governor Abbott's August 3, 2026 directive asked the Commission and ERCOT to complete a comprehensive verification and audit of data centers in the interconnection process. In response, ERCOT paused the Batch Zero study process and paused approvals to energize data centers and crypto mining facilities of 75 MW or more. Conditional classifications sent to transmission providers on September 3, 2026 included 204 projects (66.4 GW) as base load and 158 projects as studied load, and excluded 373 projects (302.2 GW). Final inclusion will follow the verification and audit, to be provided in December. ERCOT says it is still determining the impact on the study timeline, which PGRR 145 originally set to finish by April 9, 2027. The item was for information only, with no Board action requested. ERCOT Board of Directors, Item 14: Batch Zero Update (September 14-15, 2026)
- August 3, 2026, ERCOT: Batch Zero classification delayed after Governor's letter. ERCOT says it received a letter from Governor Greg Abbott directing it to conduct a verification process before advancing any data center large loads. As a result, it will not notify distribution and transmission service providers by August 7, 2026 of how any large load is classified in the Batch Zero Interconnection Study. Ahead of the Commission's August 20, 2026 open meeting, it will file a request for a good cause exception to the Batch Zero timelines and processes in its Planning Guide. The notice does not mention energization approvals; it says ERCOT will consult with the Commission on next steps. ERCOT Market Notice M-A080326-01, Update Regarding Batch Zero Timelines and Processes
- May 18, 2026, ERCOT: ERCOT asks to adjust its 2026 long-term load forecast before using it. ERCOT filed with the Commission a proposal to adjust its 2026 preliminary long-term load forecast before using it in transmission planning and resource adequacy studies, including the 2026 Triennial Reliability Assessment. The preliminary forecast projects peak load of 278,003 MW in 2029 and 367,790 MW in 2032. ERCOT offers two options: an adjustment based on how many computational large loads actually energized when expected, or use of the Batch Zero load forecast. It recommends the Batch Zero option, which it says would not be finalized until mid-August 2026. The notice is a proposal; the Commission was scheduled to consider it at its June 18, 2026 open meeting, in Project No. 59772. ERCOT Market Notice M-B051826-01, Proposal to Adjust 2026 Long-Term Load Forecast
Next public dates
- December 10, 2026: ERCOT files its Batch Zero Eligibility Verification Report and its Community Impact Review Report with the Commission. ERCOT Board of Directors, Item 14: Batch Zero Update (September 14-15, 2026)
- December 31, 2026: Senate Bill 6 deadline for the Commission to amend its rules so wholesale transmission charges appropriately assign costs for transmission investment (Project No. 58000). ERCOT, 89th Legislative Session: ERCOT Status (October 2026)
Data center projects GridTilt records here
From Compute Frontier records, each with its own sources. An estimate marks a GridTilt estimate or an announced target not yet realized.
- Sailfish Comanche Circle: Sailfish Digital Ventures, Tolar; announced, 5,000 MW planned (estimate or announced target); not yet reviewed field by field.
- IREN Sweetwater Hub: IREN, Sweetwater; under construction, 2,000 MW planned; not yet reviewed field by field.
- Microsoft Pecos: Microsoft, Pecos; announced, 2,000 MW planned; not yet reviewed field by field.
- Poolside Project Horizon: Poolside, Fort Stockton; announced, 2,000 MW planned (estimate or announced target); not yet reviewed field by field.
- PowerHouse-Provident DFW Hyperscale Campus: PowerHouse Data Centers, Grand Prairie (Ellis County); under construction, 1,800 MW planned (estimate or announced target); not yet reviewed field by field.
- Galaxy Helios: Galaxy Digital, Dickens County; operating, 1,600 MW planned; not yet reviewed field by field.
- GridFree South Dallas One: GridFree AI, Hill County; announced, 1,500 MW planned (estimate or announced target); not yet reviewed field by field.
- Stargate Shackelford: OpenAI / Oracle, Shackelford County; under construction, 1,400 MW planned; not yet reviewed field by field.
- CloudBurst San Marcos Data Center I: CloudBurst Data Centers, San Marcos; under construction, 1,200 MW planned; not yet reviewed field by field.
- Nscale Cedarvale: Nscale, Barstow; under construction, 1,200 MW planned (estimate or announced target); not yet reviewed field by field.
- Stargate Abilene: OpenAI / Oracle, Abilene; operating, 1,200 MW planned; reviewed field by field September 28, 2026.
- Stargate Milam County: OpenAI / Oracle, Milam County; under construction, 1,200 MW planned; not yet reviewed field by field.
- Goodnight Campus: Crusoe (for Google), Claude; under construction, 1,000 MW planned (estimate or announced target); not yet reviewed field by field.
- Hut 8 Beacon Point AI Data Center Campus: Hut 8, Robstown; under construction, 1,000 MW planned (estimate or announced target); not yet reviewed field by field.
- Meta El Paso: Meta, El Paso; under construction, 1,000 MW planned; not yet reviewed field by field.
- Meta Temple: Meta, Temple; operating, 1,000 MW planned (estimate or announced target); not yet reviewed field by field.
- Taylor Technology Campus: Big Watt Digital / PowerHouse Data Centers, Taylor; announced, 1,000 MW planned; not yet reviewed field by field.
- Crusoe Abilene II: Crusoe, Abilene; under construction, 900 MW planned; not yet reviewed field by field.
- Google Meitner Energy Center: Google, Pampa; under construction, 840 MW planned (estimate or announced target); not yet reviewed field by field.
- Sailfish Kyle Campus: Sailfish Digital Ventures, Kyle; announced, 800 MW planned (estimate or announced target); not yet reviewed field by field.
- Sailfish New Braunfels Campus: Sailfish Digital Ventures, New Braunfels; announced, 800 MW planned (estimate or announced target); not yet reviewed field by field.
- AWS Northlake: Amazon (AWS), Northlake; under construction, 600 MW planned (estimate or announced target); not yet reviewed field by field.
- CloudHQ SAT Campus: CloudHQ, San Antonio; under construction, 600 MW planned (estimate or announced target); not yet reviewed field by field.
- Google Haskell County Campus: Google, Haskell County; under construction, 600 MW planned (estimate or announced target); not yet reviewed field by field.
- Riot Platforms Corsicana AI/HPC Campus: Riot Platforms, Corsicana; under construction, 600 MW planned (estimate or announced target); not yet reviewed field by field.
- Yondr Lancaster Campus: Yondr Group, Lancaster; announced, 550 MW planned (estimate or announced target); not yet reviewed field by field.
- Aligned Project Caprock: Aligned Data Centers, Abernathy (Hale County); under construction, 540 MW planned; not yet reviewed field by field.
- Tesla Cortex 2: Tesla, Austin; operating, 500 MW planned; not yet reviewed field by field.
- DataBank Red Oak Campus: DataBank, Red Oak; under construction, 480 MW planned; not yet reviewed field by field.
- CyrusOne Bosque County Campus: CyrusOne, Whitney; under construction, 400 MW planned (estimate or announced target); not yet reviewed field by field.
- Prime Lockhart: Prime Data Centers, Lockhart (Caldwell County); announced, 384 MW planned; not yet reviewed field by field.
- Cipher Barber Lake AI Campus: Cipher Mining, Colorado City; under construction, 300 MW planned (estimate or announced target); not yet reviewed field by field.
- Cipher Black Pearl: Cipher Mining, Wink; under construction, 300 MW planned; not yet reviewed field by field.
- Google Midlothian Data Center: Google, Midlothian; operating, 300 MW planned (estimate or announced target); not yet reviewed field by field.
- Rowan Project Temple: Rowan Digital Infrastructure, Temple; under construction, 300 MW planned; not yet reviewed field by field.
- Soluna Project Dorothy 3 AI/HPC Campus: Soluna, Silverton; announced, 300 MW planned (estimate or announced target); not yet reviewed field by field.
- Soluna Project Kati AI/HPC Campus: Soluna, Raymondville; operating, 300 MW planned (estimate or announced target); not yet reviewed field by field.
- CleanSpark Austin County AI Data Center Campus: CleanSpark, Bellville; under construction, 285 MW planned (estimate or announced target); not yet reviewed field by field.
- Core Scientific Denton HPC Data Center: Core Scientific, Denton; operating, 260 MW planned (estimate or announced target); not yet reviewed field by field.
- Meta Fort Worth Data Center: Meta, Fort Worth; operating, 250 MW planned (estimate or announced target); not yet reviewed field by field.
- Texas Critical Data Centers: New Era Energy & Digital, Odessa; under construction, 250 MW planned (estimate or announced target); not yet reviewed field by field.
- EdgeConneX Cedar Creek Campus: EdgeConneX, Cedar Creek; under construction, 240 MW planned (estimate or announced target); not yet reviewed field by field.
- STACK South Dallas Campus: Stack Infrastructure, Lancaster; under construction, 220 MW planned; not yet reviewed field by field.
- CyrusOne DFW7: CyrusOne, Fort Worth; under construction, 200 MW planned; not yet reviewed field by field.
- IREN Childress: IREN, Childress; operating, 200 MW planned (estimate or announced target); not yet reviewed field by field.
- Riot Platforms Rockdale AI Data Center: Riot Platforms, Rockdale; under construction, 200 MW planned (estimate or announced target); not yet reviewed field by field.
- TeraWulf Abernathy HPC Campus: TeraWulf, Abernathy; under construction, 168 MW planned (estimate or announced target); not yet reviewed field by field.
- Soluna Project Kati: Soluna, Willacy County; under construction, 166 MW planned (estimate or announced target); not yet reviewed field by field.
- Sabey SDC Austin: Sabey, Round Rock; operating, 138 MW planned (estimate or announced target); not yet reviewed field by field.
- Tesla Cortex 1: Tesla, Austin; operating, 130 MW planned; not yet reviewed field by field.
- Cipher Stingray AI Data Center: Cipher Mining, Andrews; under construction, 100 MW planned (estimate or announced target); not yet reviewed field by field.
- Lambda at Aligned DFW-04 - Plano: Lambda, Plano; under construction, 72 MW planned; not yet reviewed field by field.
- Element Critical Houston One: Element Critical, Katy; under construction, 36 MW planned; not yet reviewed field by field.
- Flexential Plano: Flexential, Plano; operating, 13 MW planned; not yet reviewed field by field.
- Denvr Dataworks Houston: Denvr Dataworks, Houston; operating, 10 MW planned (estimate or announced target); not yet reviewed field by field.
- Google Red Oak Data Center: Google, Red Oak; operating; not yet reviewed field by field.
- Microsoft San Antonio (Castroville / Medina) Campus: Microsoft, Castroville; under construction; not yet reviewed field by field.
GridTilt's facility map covers campuses of 400 MW and up and lists 4 in Texas. Neither list is a complete count of the state's data centers; a project missing here is not evidence that none exists.
What this page cannot tell you about a bill
In the competitive retail areas of the ERCOT region, a home buys electricity from a retail electric provider. The provider buys electricity from generation companies, and it buys delivery service from the transmission and distribution utility whose power lines serve the home, such as Oncor. The Public Utility Commission sets those utilities' transmission and distribution rates. Municipal utilities and electric cooperatives (with a few exceptions such as Lubbock), and utilities outside the ERCOT region, kept the older structure in which one utility provides generation, delivery and retail service (Texas Sunset Advisory Commission, PUC and ERCOT Staff Report (November 2022), Introduction: Texas Electricity Primer). A statewide residential average blends every utility's residential customers, and nothing on this page shows how much any project or power line added to a household's bill. EIA publishes the averages by state: Electric Power Monthly, Table 5.6.A.